Better safe than sorry? Why Resurrection Church Aptos CA must remodel Markey Community Center ASAP

Better safe than sorry?  Why Resurrection Church Aptos CA  must remodel their Community Center ASAP.

Tom Hogan, a member of the parish,  spoke  at Resurrection Church 3/23/2000 on Why Now and How the Remodel of Markey Community Center will proceed.  Tom Hogan is on the Steering Committee guiding the remodel effort.  He  detailed the necessary safety issues which must be addressed.

The hub for Resurrection Church — their community center — requires extensive  changes to make it safe for volunteers, staff and the persons served. Resurrection Church provides many ministries to youth, seniors and vulnerable persons.

One vulnerable person served:  Many non-profit organizations including Boy Scouts use the Community Center to provides services used by the Aptosian community.  Click  Here for a brief  video of a Boy Scout project located on Resurrection’s grounds which, when the video was taken, provides temporary  shelter for a homeless person.

Why is the proposed remodel of  Resurrection Church’s community center so expensive?   Safety is the prime reason for the expensive remodel:  the expected  cost    $5.5 MILLION.

Safety issues:   Resurrection Church’s community center is a  55 year old building, separate from the church proper, which has asbestos in the walls and ceiling and  paint with lead in it  on the walls.  The building floods on occasion due to stormy weather.  Recently, a large tree fell one corner of Markey Community Center, disabling the Center for a few days and  ‘yellow tagging’  Resurrection Church’s  children’s playground which is currently not safe to use.   Volunteers and staff need to be able to exit safely should there be an emergency such a as  a dangerous person confronting them.  them.  Federal  OSHA law requires exit routes be mantaotry.  The ceiling requires a sprinkler system.  The bathrooms need to meet health codes and must  be safe for persons in wheel chairs.

Resurrection Church has THE PLAN which it has been following to gather the necessary money needed prior to start of construction.  For information on Resurrection Church’s website click HERE for the Resurrection Catholic Church 2020 Campaign.

THE PLAN:  

  1. Identify  prospects  who can make  large  Leader Gifts.   So far, parishioners have given large and smaller gifts totaling  $1 MILLION of the $5.5 needed. About 1/2 the Goal towards Leader Gifts has been met.   
  2.  Identify  prospects for Foundation Grants.  This is ongoing.  As of 3/15/2000 no Foundations have said Yes.
  3. Identify prospects for Community (business) Gifts.
  4. Contact the parish members who have not yet given

This post will be updated when more information becomes available.

In response to the coronavirus pandemic  Resurrection Church was required by the Diocese to cancel   the  meeting for Volunteers scheduled for today 3/14/2000.   Also,  the Church was required to cancel various fundraisers including Sunday Icecream Social and Eat, Drink and Give.

Resurrection Church’s grounds include places for repose,  places  to sit and enjoy the beauty  of the setting. One such spot I call Art from the Heart located in front of the Handicapped Parking.  Click Here for a brief video of Art from the Heart.

Like more information?   Go to  www.renewmarkeycommunitycenter.org

written by Cameron Jackson

 

 

Share